Railway projects move at slow speed

Updated: 2011-11-10 11:30

By Xin Dingding (China Daily)

  Comments() Print Mail Large Medium  Small 分享按鈕 0

BEIJING - A number of high-speed railway projects slated to open this year will have their big day postponed to next year or later, railway construction companies said.

A 200 km/h railway between Hefei and Bengbu in East China's Anhui province was set to be ready for operation by Nov 20 this year, but its debut has been postponed to next year, said an official with China Railway 4th Group Co Limited, insisting on anonymity.

"Work on the project is still on ... but on a small scale, not in full swing," he said.

A publicity official with the company said that the tracks could not be completely laid because of a money crunch that the railways ministry faces.

"According to the contracts, the rails we lay out are provided by the project company established by the ministry. But it failed to provide the rails to us on time. That's why we still have not finished laying the tracks," she said.

Another rail project the company is involved in - the 350 km/h Shijiazhuang-Wuhan railway - is also set to have its opening postponed from this year to next year or later, she said.

The laying of the tracks for the 840-km line, part of the north-south trunk line connecting Beijing, Guangzhou and Shenzhen, is complete. But the remaining work, such as testing the project's electricity supply, is not finished yet, she said.

Zhang Cheng, deputy general manager of China Railway 11th Bureau Group Co Ltd, was quoted by Xinhua News Agency as saying that the delay resulted from railway authorities' carrying out national railway-safety overhauls after the Wenzhou train crash in July that killed 40 passengers.

The safety checkups led to those projects making a slow progress, Zhang said.

Xinhua reported that apart from the Shijiazhuang-Wuhan railway, three other railways coming out of Wuhan, capital of Central China's Hubei province, have been delayed too.

In Northeast China, a railway linking Harbin and Dalian, which is scheduled to open this year, is also sure to be delayed, because work on the line has been suspended since the accident and has not resumed yet, said an official with Shenyang railway bureau, who spoke on condition of anonymity.

"In the past, speed was the most important thing. Nowadays, safety is the priority," he said.

After the deadly crash, Sheng Guangzu, the railway minister, ordered a slowing down of the speed of all bullet trains and stressed that there should be no rush to finish construction work earlier than the stipulated period.

Insiders believe that the widespread delay in making new lines operational is also caused by a fund shortage faced by the ministry.

The Ministry of Railways was reportedly unable to raise enough money to support the extensive railway construction spanning more than 10,000 km, as the cash flow was tightened and its reputation took a beating following the accident.

But now with a fresh allotment of 200 billion yuan ($31.6 billion) from the central government, the railways ministry has promised to pay off some of its creditors before Nov 20 to guarantee the progress of key projects. On Tuesday, it auctioned 30 billion yuan worth of bonds.

Still, the delay from this year to next year comes as a blow to some passengers who had expected to go on board fast trains soon.

Cui Li, a 23-year-old woman in Bengbu of Anhui province, who travels to Hefei on business once a month, said she took a two-to-three hour bus ride between the two cities.

"The new train service would take only 40 minutes (to cover the distance). The train currently available is an old one. It is really unpleasant to ride on," she said.

"I heard the delay was to ensure safety, but the likelihood of high-speed train accidents is extremely small, almost the same as that on plane rides. My colleagues and I care more about convenience," she said.

But others supported the ministry's new emphasis on safety.

Chen Tianhong, a 24-year-old student at Wuhan University from Jiangxi province, said it was very thoughtful of the government to delay opening new lines out of safety concerns.

"A rapid expansion of transportation infrastructures will bring about more disasters someday. Safety issues require more attention than speed," he said.

主站蜘蛛池模板: 亚洲国产第一 | aa级毛片毛片免费观看久 | 日韩精品一区二区三区免费视频 | 九九在线观看视频 | 亚洲视频免费观看 | 久久怡红院国产精品 | 欧美一区二区三区免费高 | 草草在线观看视频 | 在线精品播放 | 91视频一区 | 美国一级毛片片aaa 美国一级毛片片aa成人 | 欧美成人高清在线视频大全 | 九九在线免费观看视频 | 国产精品黄网站 | 一级黄色香蕉视频 | 久爱免费观看在线网站 | 日韩一级黄色 | 毛片网站观看 | 一区二区三区视频在线观看 | 精品一区视频 | 精品综合久久久久久蜜月 | zztt40.su黑料不打烊官网 | 日韩3级 | 亚洲精品久久九九热 | 高清国产露脸捆绑01经典 | 国产精品久久福利网站 | 在线观看人成网站深夜免费 | 高清国产在线播放成人 | 久久久一区二区三区不卡 | 小明日韩在线看看永久区域 | 国产欧美日韩高清专区手机版 | 欧美a欧美| 国产美女在线精品亚洲二区 | 日韩免费高清一级毛片在线 | 黄色在线视频网 | 国产超清在线观看 | 久久欧美精品欧美久久欧美 | 视频一二三区 | 国产精自产拍久久久久久蜜 | 国产精选91热在线观看 | 亚洲三级在线看 |