Home> Local
Water diversion project back on fast track
By Liang Chao ( chinadaily.com.cn )
Updated: 2011-02-25

More than 52 billion yuan ($7.9 million) is expected to be injected into the South-to-North Water Diversion Project this year, the largest ever since the ambitious plan was kicked off eight years ago but delayed due to complicated issues.

E Jingping, top official at the office in charge of the program's construction under the State Council, announced at a conference on Thursday (Feb 24) that, in 2011, authorities will pour a record 52 billion yuan into the project, with maximum investment to exceed 60 billion yuan.

Of the fund, 33 billion yuan will be earmarked for projects in the eastern and central routes to be launched this year, with the rest to be spent on speeding up the shift of some 190,000 people slated to make way for the new water canals of the central route.

Most of them are in Central China's Hubei and Henan provinces.

To achieve the goal set for this year, E (an uncommon family name in China, most popular in Hubei province) made it clear that local authorities should have ensured engineering progress in full sail, keep an eye on quality control, bring investment under effective control and resolve key technological problems facing the project such as swelling soil.

Also known as dilative soil or expensive soil, the problem potentially endangers up to 357 kilometers of the planned open water supply channel, or one-third of the total the central route has to go across in central China.

In the eastern route, authorities must improve water pollution control with water quality in all sections reaching grade III, the minimum standard for drinking water after being treated.

Water quality of Danjiangkou Reservoir, which will feed the main central route and areas upstream, should be up to the grade II the government set for surface water.

E urged local authorities to team up with other related authorities to deal with possible conflicts of interest as the vast water diversion project has been in "the most critical period of its construction".

The construction of the first phase of the water diversion is at risk.

Over the past eight years, only 33 individual projects out of 155 were completed, with 31 others failing to start work as scheduled, sources with E's office disclosed.

It meant that only about one-third of the phase's total investment was realized, with the remaining two-thirds having to be completed in the three years ahead.

As the world's largest water-diversion project, the project is to take water from the water-rich Yangtze River in the South to satisfy the growing demand in the parched North, including metropolises such as Beijing, Tianjin and scores of other drought-prone cities through its three routes - the eastern, central and western water diversion channels, each stretching over 1,000 km.

The first phase of the two routes has been under construction since 2002 and 2003, with the last one still on the drawing board.

Years later, their construction has been bogged down due to issues surrounding investment and complicated economic and social factors such as rising prices.

As a result, the planned completion of the first stage of the eastern and central routes was pushed back to 2013 and 2014, respectively, after it became clear that the earlier deadlines of 2010 and 2008 could not be met.

Since then, the plan has been pushed onto the fast track again, with construction in many branch sections getting into full swing. Last year, work was started on 40 delayed individual projects, with 48 billion yuan of investment involved, while the resettlement program and water pollution control, two of the decisive factors for the success of the vast water diversion project, were also pushed forward.

Last year, some 149,000 people, or 43 percent of the total slated to make way for the enlarged Danjiangkou Reservoir area, were resettled, while water quality in 83 percent of the sections the authorities have surveyed along the eastern route were reportedly up to standards, according to insiders.

 
Video
Specials



 
 
主站蜘蛛池模板: 亚洲日本一区二区三区高清在线 | 国产亚洲福利精品一区二区 | 国产在线观看免费一级 | 日韩成人免费在线视频 | 国产免费一级精品视频 | 黄色wwwwww| 伊人22综合| 久久精品免费i 国产 | 欧美成人综合在线观看视频 | 亚洲日韩aⅴ在线视频 | 5x社区直接进入一区二区三区 | 亚洲欧美在线观看播放 | 在线日韩欧美一区二区三区 | 在线 | 一区二区三区 | 中文字幕一区二区三 | 亚洲国产另类久久久精品小说 | 97精品福利视频在线 | 久久午夜影视 | 中日韩欧美一级毛片 | 一级毛片免费观看视频 | 精品国产免费一区二区三区 | 欧美人在线一区二区三区 | 真人一级一级特黄高清毛片 | 欧美人交性视频在线香蕉 | 国产精品高清免费网站 | 久久免费在线视频 | 欧美精品一二三区 | 久久九九国产 | 在线a网站 | 亚洲网址在线 | 中文字幕中文字幕在线 | 男人天堂久久 | 在线观看亚洲人成网站 | 99久久精品毛片免费播放 | 国产综合在线视频 | 欧美成成人免费 | 国产成人高清精品免费软件 | 国产或人精品日本亚洲77美色 | 国产三级在线免费 | 永久免费精品视频 | 一区二区三区中文国产亚洲 |