Nuclear plant gets approval from top regulator

By LYU CHANG (China Daily) Updated: 2015-04-09 07:38

Nuclear plant gets approval from top regulator

The Fuqing nuclear power plant is under construction. The concrete for the reactor at the nuclear project in Fujian province is likely to be poured in the first half of this year. [Photo/China Daily]

The fifth and sixth units of the Fuqing nuclear power plant, which uses the Hualong One reactor design, known as the third-generation nuclear technology, got the green light from the National Development and Reform Commission on Wednesday, signaling one step closer to the export of Chinese nuclear technology, industry sources said.

"Though the project still needs final approval from the State Council to start construction, the green light will aid the bidding process in overseas countries, as it shows confidence in China's capabilities to develop its own nuclear technology," an unidentified source at a State-owned nuclear company told China Daily.

The concrete for the reactor at the nuclear project in China's Fujian province is likely to be poured in the first half of this year, the source said, adding that two-thirds of the equipment purchase order is complete.

The approval, which came after construction began at the Hongyan River nuclear power plant in March, is set to make Fuqing the first nuclear project that will use the third-generation nuclear technology after the Fukushima nuclear disaster in Japan four years ago.

Experts said that the government is likely to give more "green lights" for new nuclear power projects this year, as the country wants to leverage its home experience to export nuclear technologies with independent intellectual property right.

China National Nuclear Corporation, the biggest owner of the Fuqing nuclear power project, is promoting the Hualong One design to countries with huge market potential such as Argentina and Turkey. The Fuqing nuclear power plant construction will also help the company bid for projects in these countries, experts said.

The Fuqing plant will eventually house six Chinese-designed pressurized water reactors. The first four units of the plant are Chinese-developed CPR-1000 reactors. Unit 2, construction of which began in June 2009, is expected to start operating in August.

The first unit of Fuqing nuclear power plant reached full capacity last year.

Remy Autebert, senior executive vice-president for the Asia-Pacific region at Areva, the French nuclear giant, said that China is accelerating construction of nuclear projects with 6 to 8 new reactors going on stream every year.

"Even before the Fukushima nuclear disaster in 2011, China had outpaced that growth rate," he said. "So the country is clearly building more than that."

China currently has 22 nuclear power reactors in operation with an installed capacity of about 17 gigawatts. A further 26 units are under construction, with combined capacity totaling almost 30 gW.

After the Fukushima disaster, China suspended approval for nuclear plants in order to revise its safety standards. However, it lifted the ban on new nuclear power stations at the end of 2012, and said it would only approve projects proposed for coastal areas within 2015.

Hot Topics

Editor's Picks
...
主站蜘蛛池模板: 国产真实生活伦对白 | 成人a在线观看 | 国产日本欧美在线观看 | 97在线观看免费版 | 国产成人午夜性视频影院 | 成人一级片 | 国产亚洲精品成人久久网站 | 亚洲在线观看免费 | 青青自拍视频一区二区三区 | 日韩视频一区二区 | 艳女伦交一级毛片 | 欧美日韩专区国产精品 | 亚洲成a人片在线观看精品 亚洲成a人片在线观看中 | a毛片免费| 四虎午夜剧场 | 一级毛片不卡免费看老司机 | 99在线视频精品 | 呦视频在线一区二区三区 | 欧美久 | 国产美女又黄又爽又色视频免费 | 国产网址在线 | 午夜三级网| 国内一级野外a一级毛片 | 99热久久精品免费精品 | 国产三级香港三韩国三级 | 久久一本精品久久精品66 | 免费国产成人手机在线观看 | 香蕉超级碰碰碰97视频蜜芽 | 国产aⅴ精品一区二区三区久久 | 97香蕉久久夜色精品国产 | 欧美日韩国产亚洲一区二区三区 | 日本αv| 国产成人综合久久精品红 | 国产亚洲精品成人久久网站 | 成人在线观看一区 | 成人在线观看午夜 | 欧美亚洲日本视频 | 午夜mm131美女做爰视频 | 国产99视频精品免费视频7 | 成人看片黄a毛片 | 香港激情三级做爰小说 |