Rising to a tunnel's challenge

By China Daily | China Daily | Updated: 2017-06-09 07:32

Rising to a tunnel's challenge

Workers deal with gushing water during the construction of the Dazhushan Tunnel on the Dali-Ruili Railway project in May.Provided To China Daily

When work began on the Dazhushan Tunnel, the plan was to finish it in five years. That was in 2008 - and construction crews are still digging.

Unexpected difficulties mean the 14.5-kilometer tunnel, a critical juncture on the Dali-Ruili Railway in Yunnan province, is now scheduled for completion in 2021, Xinhua News Agency reported.

The tunnel runs through six faults in the Hengduan Mountains on the Qinghai-Tibet Plateau. It would have been beyond imagination to build on the earth fractures 20 years ago, said You Hongsheng, a spokesman for No 4 Company of China Railway First Group Co, which is digging the tunnel.

Rising to a tunnel's challenge

In August 2009, immediately after the first drilling began at one of the six fault lines, a 20-centimeter crack appeared in the operating face. The crack continued to widen as mudrock gushed out, filling a space 200 meters long and 6 meters high in about five hours.

"We failed to predict the fragility of the fault," said Jiang Dong, a construction manager at the site. "It is just like drilling into a piece of bean curd. The mudrock started to flow into the tunnel as we worked."

Jiang said the problem was later solved by building a wall to stop the mudrock flow and grouting the flow until it became solid. "Then we dug through the solid part to carry on with the project."

Rising to a tunnel's challenge

?

An estimated 140 million cubic meters of water have been pumped out of the tunnel over the past nine years of construction work.

In addition to the day-to-day operating challenges, the geologic complexity of the area where the tunnel is located has made working conditions extremely tough for workers.

In most parts of the construction site, it's quite humid, with the temperature in the hole at around 37 C. Workers had to alternate in two-hour shifts to continue through the day.

Some workers have left the project because of the rough working conditions and the extended construction time. Others, however, stayed put and were determined to hold their ground until the tunnel's completion.

Jiang said when he began working at the site his daughter was in second grade, and now she is in senior high school. He has been able to be home for just 20 days every year.

Wu Hao, 25, chose to stay with the project even though his father needed him in the family business.

"I need to prove myself in this project. How can I give up halfway?" Wu said.

When the Dali-Ruili Railway is complete, it will take a train just five minutes to run through the tunnel. Few passengers will know that it took 13 years to build.

 

Editor's picks
Copyright 1995 - . All rights reserved. The content (including but not limited to text, photo, multimedia information, etc) published in this site belongs to China Daily Information Co (CDIC). Without written authorization from CDIC, such content shall not be republished or used in any form. Note: Browsers with 1024*768 or higher resolution are suggested for this site.
License for publishing multimedia online 0108263

Registration Number: 130349
FOLLOW US
 
主站蜘蛛池模板: 久久精品一区二区三区中文字幕 | 国产成人精品免费视频大 | 亚洲一区二区三区四区五区六区 | 四川一级片 | 嫩模大尺度人体福利视频 | 精品国产一二三区 | 国产成人精选免费视频 | 亚洲男人在线 | 中文三级视频 | 免费黄色网址在线播放 | 草草影院ccyycom浮力影院 | 青草青99久久99九九99九九九 | 国内精品久久久久久久影视麻豆 | 一本色道久久88加勒比—综合 | 亚洲国产欧美日韩精品一区二区三区 | 国产欧美17694免费观看视频 | 日韩一级在线 | 一级欧美| 91av国产在线 | 亚洲男人的天堂久久无 | 国产亚洲精品久久久久久久网站 | 国产精品分类视频分类一区 | 99久久精品国产自免费 | 一区二区国产精品 | 中文字幕乱码系列免费 | 国产黄色片在线免费观看 | 九九亚洲精品自拍 | 国产精品久久久久久久久免费 | 久久青草热 | 色拍拍在精品视频69影院在线 | 美国一级毛片免费看成人 | 最新国产精品视频免费看 | 欧美日韩中文字幕在线观看 | 亚洲男女免费视频 | 国产午夜亚洲精品国产 | 欧美成人免费午夜影视 | 精品日韩欧美一区二区三区在线播放 | 午夜看片网站 | 国产精品久久久久久久久免费观看 | 亚洲一区视频在线 | 亚洲国产系列 |